Boys Camp Road Temporary Bridge Update

Boys Camp Road Bridge Update

For those who live beyond Boys Camp Road, you are aware that a temporary bridge has been planned.  A gravel bridge will be built next week in the same location as the temporary ford.  

  • The temporary bridge will include 5 culverts and it will be elevated above the water.   
  • Crews will be working to level out the bridge so it has less of an incline.
  • Constructing the bridge will take about 48 hours and the road will not be passable during this time.
  • The Fire Department will stage emergency vehicles beyond the bridge to provide support as needed during the 48 hour timeframe.  
  • The date for the road closure and construction will be confirmed as soon as possible. 
  • We are currently awaiting materials to begin the project and confirm the date for the temporary road closure. 

Additionally, we are obtaining design specifications for a permanent Boys Camp Road Bridge.  

Thank you for your patience as we work through the recovery process. 

For questions you may email Communications@townoflakelure.com 

Update 11/6/24

FOR THOSE NEEDING TO DEPART DURING CONSTRUCTION: 

A walking path will be set up for anyone needing to be able to leave the area during construction.  

Firefighters will be available during specified time periods to assist anyone needing to walk over the path.

A parking area will be available at the field at Sheridan Lane and Boys Camp Road so cars may be left for anyone needing to leave during construction. 

For assistance or coordination coming and going during construction: Please send an email to the following address and we will work with you. Email Communications@townoflakelure.com(Subject: Boys Camp Road Bridge Crossing)