Lake Lure Reservoir Drain Project Update 10/5/23
This has been a productive week for the Lake Lure Reservoir Drain Project.
- A permit has been secured for the construction trailer.
- Culvert Pipes were delivered for the temporary construction crossing in the river to access the back side of the dam.
- Equipment was delivered to start excavation.
- On 10/5/23, excavation began to prepare the site for the temporary crossing.
Excavation Begins 10/5/23
Lake Lure Reservoir Drain Culvert Pipes Arrive