The 2023 Lake Drawdown Schedule was announced at Town Council on 7/12/22 and was widely publicized. The lake began lowering on 1/1/23 as planned in support of several important infrastructure projects.
It is anticipated that the lake will begin refilling on 3/31/23. The rate of refilling the lake is dependent upon weather conditions but information will be posted here regarding weekly lake levels.
Lake levels will vary during the drawdown between 5 feet below full pond and 12 feet below full pond, depending on the work requirements of contractors.
A list of projects to be completed during the lake drawdown is listed below:
- Beginning of Phase One of the sewer system replacement project. This will include boring pipe sleeves on properties in the Sunset Cove area.
- Lake dredging with excavators
- Seawall repair/replacement
- Penstock inspection and warrantee repairs
- Work on deep water access ramp near the dam
NOTE: Contractors working on seawall repairs/replacement must be out of the lake by 3/15/23.