Boys Camp Road Temporary Bridge Update

Boys Camp Road Bridge Update

For those who live beyond Boys Camp Road, you are aware that a temporary bridge has been planned.  A gravel bridge will be built next week in the same location as the temporary ford.  

  • The temporary bridge will include 5 culverts and it will be elevated above the water.   
  • Crews will be working to level out the bridge so it has less of an incline.
  • Constructing the bridge will take about 48 hours and the road will not be passable during this time.
  • The Fire Department will stage emergency vehicles beyond the bridge to provide support as needed during the 48 hour timeframe.  
  • The date for the road closure and construction will be confirmed as soon as possible. 
  • We are currently awaiting materials to begin the project and confirm the date for the temporary road closure. 

Additionally, we are obtaining design specifications for a permanent Boys Camp Road Bridge.  

Thank you for your patience as we work through the recovery process. 